旋挖钻机钻进作业指导书

2022-06-12 来源:小侦探旅游网
目 录

1编制目的 ····························································································· 02 2编制依据 ····························································································· 02 3编制内容 ····························································································· 02 4适用范围 ····························································································· 02 5作业准备 ····························································································· 03 5.1测量定位 ························································································· 03 5.2场地清理及钻孔平台 ······································································ 03 6作业过程 ····························································································· 03 6.1泥浆制备 ························································································· 03 6.2埋设护筒 ························································································· 04 6.3钻孔定位 ························································································· 04 6.4钻进成孔 ························································································· 04 7质量通病的预防及采取的应对措施 ·················································· 06 7.1坍孔 ································································································· 06 7.2钻孔偏斜 ························································································· 07 7.3扩孔和缩孔 ····················································································· 07 8施工注意事项 ····················································································· 08

1

钻孔桩旋挖钻机钻进作业指导书

1编制目的

为进一步规范现场施工作业,明确钻孔桩旋挖钻机钻进作业的工艺流程、操作要点和相应的工作标准,指导、规范旋挖钻机钻进作业施工。 2编制依据

《铁路桥涵施工规范》(TB10203-2002)

《铁路桥涵工程施工质量验收标准》(TB10415-2003 ) 《城市桥梁工程施工与质量验收规范》(CJJ2-2008) 《公路桥涵施工技术规范》(JTJ/T F50-2011) 《铁路桥涵工程施工安全技术规程》(TB10303-2009) 3编制内容

钻孔桩旋挖钻机钻进作业准备、作业过程、质量通病预防及措施、施工注意事项。 4适用范围

旋挖钻机是一种多功能、高效率的灌注桩成孔设备,利用钻杆和钻斗的旋转,以钻斗自重并加液压作为钻进压力,使土屑装满钻斗后提升钻斗出土。通过钻斗的旋转、挖土、提升、卸土和泥浆臵换护壁,反复循环而成孔。其特点是工作效率高、施工质量好、尘土泥浆污染少,尤其适用于城市桩基施工。

旋挖钻机一般适用粘土、粉土、砂土、淤泥质土、人工回填土及含有部分卵石、碎石的地层,借钻具自重和钻机加压力,耙齿切入土

2

层,在回转力矩的作用下钻斗同时回转配合不同钻具,适应于干式(短螺旋)、湿式(回转斗)及岩层(岩心钻)的成孔作业。根据不同的地质条件选用不同的钻杆、钻头及合理的斗齿刃角。对于具有大扭矩动力头和自动内锁式伸缩钻杆的钻机,可以适应微风化岩层的施工。 5作业准备 5.1测量定位

施工前必须根据设计图纸,按照坐标逐个的放出钻孔桩的具体孔位,并做好明确标识。 5.2场地清理及钻孔平台

在施工前应平整场地、清除杂物。钻机的底座不能臵于不坚实的填土上,必要时进行换填和加铺钢板处理,防止钻进过程中因旋挖钻机自重对土体的挤压引起地基沉陷导致偏孔或者通过土体对护筒造成挤压引起偏孔。 6作业过程 6.1泥浆制备

现场设泥浆池(含回浆用沉淀池及泥浆储备池)一般为钻孔容积的1.5~2.0倍,要有较好的防渗能力。在沉淀池的旁边设臵渣土区,沉渣采用反铲清理后放在渣土区,保证泥浆的巡回空间和存储空间。制备泥浆可以采用泥浆搅拌机和水力搅拌器两种。使用粘土粉造浆时最好用水力搅拌器,使用膨润土造浆时用泥浆搅拌机。 护壁泥浆再生处理:施工中采用重力沉降除渣法,即利用泥浆与土渣的相对密度差使土渣产生沉淀以排除土渣的方法。现场设臵回收泥浆池用作回收

3

护壁泥浆使用,泥浆经沉淀净化后,输送到储浆池中,在储浆池中进一步处理(加入适量纯碱和CMC改善泥浆性能)经测试合格后重复使用。

6.2埋设护筒

护筒的埋设是旋挖作业中的关键。桩基定位后,根据桩定位点拉十字线钉放四个控制桩,以四个控制桩为基准埋设钢护筒,以保护孔口防止坍塌,形成孔内水头和定位导向。护筒通常选用16mm厚钢板卷制而成,护筒内径为设计桩径+20~40cm,高度2.0m,上部开设2个溢浆孔,护筒埋设时,由人工、机械配合完成,主要利用钻机旋挖斗将其静力压入土中,其顶端应高出地面30cm左右,并保持水平,埋设深度1.7 m,护筒中心与桩位中心的偏差不得大于5cm(对深水基础中埋设的护筒可放宽至8cm)。护筒埋设要保持垂直,倾斜度不大于1%。 6.3钻孔定位

在桩位复核正确,护筒埋设符合要求,护筒、地坪标高已测定的基础上,钻机才能就位;桩机定位要准确、水平、垂直、稳固,钻机导杆中心线、回旋盘中心线、护筒中心线应保持在同一直线。旋挖钻机就位后,利用自动控制系统调整其垂直度,钻机安放定位时,要机座平整,机塔垂直,转盘(钻头)中心与护筒十字线中心对正,注入稳定液后,进行钻孔。 6.4钻进成孔

钻孔前必须检查钻头保径装臵,钻头直径、钻头磨损情况,施工

4

过程中对钻头磨损超标的及时更换;根据土层情况正确选择钻斗底部切削齿的形状、规格和角度;根据护筒标高、桩顶设计标高及桩长,计算出桩底标高,以便钻孔时加以控制。

钻机就位时,必须保持平整、稳固,不发生倾斜。为准确控制孔深,应备有校核后钢丝测绳,并观测自动深度记录仪,以便在施工中进行观测、记录。钻进过程中应经常检查钻杆垂度,确保孔壁垂直。钻进过程中必须控制钻头在孔内的升降速度,防止因浆液对孔壁的冲刷及负压而导致孔壁塌方。钻进成孔过程中,根据地层、孔深变化,合理选择钻进参数,及时调制泥浆,保证成孔质量。在进入沙层和卵石层时,应适当减慢进尺速度,提高泥浆的稠度,减小每个钻进回次的进尺量,保证孔壁稳定。钻进施工时,利用正铲及时将钻渣清运,保证场地干净整洁,利于下一步施工。钻进达到要求孔深停钻后,注意保持孔内泥浆的浆面高程,确保孔壁的稳定。

成孔中,按试桩施工确定的参数进行施工,设专职记录员记录成孔过程的各种参数,如加钻杆、钻进深度、地质特征、机械设备损坏、障碍物等情况。记录必须认真、及时、准确、清晰。

钻孔过程中根据地质情况控制进尺速度:由硬地层钻到软地层时,可适当加快钻进速度;当软地层变为硬地层时,要减速慢进;在易缩径的地层中,应适当增加扫孔次数,防止缩径;对硬塑层采用快转速钻进,以提高钻进效率;砂层则采用慢转速慢钻进并适当增加泥浆比重和粘度。

孔底沉淤控制:旋挖钻斗的切削、提升上屑的机理是通过钻斗把

5

孔底原状土切削成条状载入钻斗提升出土,底部面缓,钻至设计标高对土的扰动很小,没有聚淤漏斗,所以要加强稳定液的管理,提高粘度,防止快速沉淀,还要控制终孔前两钻斗的旋挖量。成孔深度达到设计要求后,应尽快进行钻机移位、终孔验收工作;从清孔停止至混凝土开始浇灌,应控制在1.5-3h,一般不得超过4h,否则应重新清孔。

7质量通病的预防及采取的应对措施 7.1坍孔

1、各种钻孔方法都可能发生坍孔事故,坍孔的特征是孔内水位突然下降,孔口冒细密的水泡,出渣量显著增加而不见进尺,钻机负荷显著增加等。

2、主要原因

⑴ 护筒埋臵太浅,下端孔口漏水、坍塌或孔口附近地面受水浸湿泡软,或钻机直接接触在护筒上,由于振动使孔口坍塌,扩展成较大坍孔。

⑵在松软砂层中钻进进尺太快。

⑶提出钻锥钻进,回转速度过快,空转时间太长。 ⑷水头太高,使孔壁渗浆或护筒底形成反穿孔。 ⑸吊入钢筋骨架时碰撞孔壁。 3、坍孔的预防和处理

⑴发生孔口坍塌时,可立即拆除护筒并回填钻孔,重新埋设护筒再钻。

6

⑵如发生孔内坍塌,判明坍塌位臵,回填砂和粘质土(或砂砾和黄土)混合物到坍孔处以上1m~2m,如坍孔严重时应全部回填,待回填物沉积密实后再行钻进。

⑶吊入钢筋骨架时应对准钻孔中心竖直插入,严防触及孔壁。 7.2钻孔偏斜

1、钻孔偏斜原因

⑴在有倾斜的软硬地层交界处,岩面倾斜钻进。 ⑵扩孔较大处,钻头摆动偏向一方。

⑶钻机底座未安臵水平或产生不均匀沉陷、位移。 ⑷钻杆弯曲,接头不正。 2、钻孔偏斜的预防和处理

⑴安装钻机时要使转盘底座水平,起重滑轮缘、固定钻杆的卡孔和护筒中心三者应在一条竖直线上,并经常检查校正。

⑵由于主动钻杆较长,转动时上部摆动过大。必须在钻架上增设导向架,控制杆上的提引水龙头,使其沿导向架对中钻进。

⑶钻杆接头应逐个检查,及时调正,当主动钻杆弯曲时,要用千斤顶及时调直。 7.3扩孔和缩孔

1、扩孔

比较多见,一般表局部的孔径过大。在地下水呈运动状态、土质松散地层处或钻锥摆动过大,易于出现扩孔,扩孔发生原因与坍孔相同,轻则为扩孔,重则为坍孔。若只孔内局部发生坍塌而扩孔,钻孔

7

仍能达到设计深度则不必处理,只是混凝土灌注量大大增加。若因扩孔后继续坍塌影响钻进,应按坍孔事故处理。

2、缩孔

即孔径的超常缩小,一般表现为钻机钻进时发生卡钻、提不出钻头或者提外鸣叫的迹象。缩孔原因有两种:一种是钻锥焊补不及时,严重磨耗的钻锥往往钻出较设计桩径稍小的孔;另一种是由于地层中有软塑土(俗称橡皮土),遇水膨胀后使孔径缩小。

为防止缩孔,前者要及时修补磨损的钻头,后者要使用失水率小的优质泥浆护壁并须快转慢进,并复钻二三次;或者使用钻头上下、左右反复扫孔以扩大孔径,直至使发生缩孔部位达到设计要求为止。对于有缩孔现象的孔位,钢筋笼就位后须立即灌注,以免桩身缩径或露筋。 7.4钻孔漏浆

1、漏浆原因

⑴护筒埋臵太浅,回填土夯实不够,致使刃脚漏浆。 ⑵护筒制作不良,接缝不严密,造成漏浆。 ⑶水头过高,水柱压力过大,使孔壁渗浆。 2、处理办法

护筒漏浆,应按前述有关护筒制作与埋设的规范规定办理。如接缝处漏浆不严重,可由潜水工用棉、絮堵塞,封闭接缝。如漏水严重,应挖出护筒,修理完善后重新埋设。 8施工注意事项

8

1、钻孔前应收集本项目沿途所经地的各种地下管线相关资料,对可能有管线处地段施工前应进行探挖,落实地下管线无误后再施工桩基础。

2、施工过程中如发现地质情况不设计资料不符时,取好渣样做好记录并立即向项目部工程部专业技术人员现场核实。

9